12/4/20 Capital Project

12/4/20 Capital Project Update
Posted on 12/04/2020
Work week of 11/23/2020 – 11/27/2020
 
Phase 2 
Edger – Substantially Complete - Worked on remaining Punch List Items. 
Boland’s – Substantially Complete .
Brosh– Substantially Complete .
Knapp – Substantially Complete.
Siracusa - Working on  Punch lists and Change Orders.
Day - working on change orders and punch lists.

Phase 3 
FAHS – Installation of trim on DES gym window trim and misc, punchlist.
Nelcorp – Misc. Punch List Items. Completed power to greenhouses.
Siracusa – Worked on, commisioning, some valve replacements, water to greenhouses, installed UV in Vestibule and Punch List Items.
Syracuse Scenery - 
Boland’s – Painted lines on the main area of the new DES Parking Lot
Day- Worked on programming, commisioning and valves.

Phase 4
FAHS –  Working on Punch lists.  Granite for Freeville currently scheduled to ship Monday from quarry to finisher.
Schuler Hass –  Working on Punch Lists
Petcosky- 
TURF Interior 
Petcosky  – Connected to main water line and sink hood was installed.
Edger - Continued painting of darkroom, reset some of the existing cabinets. 
John  Mills Electric- 

Work week of 11/30/2020 – 12/4/2020

 
Phase 2
Edger – Substantially Complete - Worked on remaining Punch List Items. 
Boland’s – Substantially Complete.
Brosh– Substantially Complete.
Knapp – Completed conections for Bus Wash door controls
Siracusa - Worked on  Punch lists and Change Orders.
Day - Worked on change orders and punch lists.

Phase 3
FAHS – Installation of trim on DES gym windows was completed, drywall in vestubl installed and some Punch List Items and COs worked on.
Nelcorp - Additional data and minor CO work, punch lists.
Siracusa - Commissioning of AHUs, CO and Punshlist work.
Syracuse Scenery -Reviewed Lighting Punchlist  and Theatrical Lighting Training on Wednesday.
Boland’s – New student drop-off and ADA area to be painted (When Weather Allows).
Day-  Working on programming, commissioning and valves.

Phase 4
FAHS –  Working on Punch lists.  Granite for Freeville shipped Monday from quarry to finisher.
Schuler Hass –  Worked on Punch Lists
Petcosky- 
TURF Interior 
Petcosky  – Installed RTU.
Edger - Working on wall trim and finishes.
John  Mills Electric-