7/20/18 Capital Project Update

7/20/18 Capital Project Update
Posted on 07/20/2018

DES

  • ICE AND WATER SHIELD AND PAPER SUBSTANTIALLY COMPLETE AT HIGH SHINGLE ROOF.

FREEVILLE

  • EXISTING COMPOSITE SHINGLE ROOF REMOVED.
  • ICE AND WATER SHIELD AND PAPER SUBSTANTIALLY COMPLETE.

MS/HS

  • ROOFING WORK CONTINUED IN G-WING.
  • AFTER SECOND RAIN IN 1 HOUR ON MONDAY NIGHT, A TEMPORARY ROOF DRAIN WAS OVERWHELMED AND THERE WAS LEAKING INTO THE BUILDING AND VARYING DEGREES OF WATER I ROOMS G-2, G-3, G-4, G-10, G-12, G-9, THE CORRIDOR AND SCIENCE STORAGE ROOM. THE MAJORITY OF THE DAMAGE WAS LIMITED TO CEILING TILES WITH A FEW BOOKS, A COUPLE SMALL APPLIANCES AND A HANDFUL OF CABINET COMPONENTS ALSO SUFFERED DAMAGE. DAMAGES ARE BEING TRACKED AND CONTRACTOR HAS RESPONDED AND IS TAKING RESPONSIBILITY.
  • NEW TRACK FENCE POSTS WERE INSTALLED.
  • AREAS OF EXISTING THIN ASPHALT AT TRACK WERE IDENTIFIED AND A PLAN FOR CORRECTION WAS DEVELOPED. THIS WILL HAVE AN IMPACT ON THE OVERALL COMPLETION DATE AND TURN-OVER OF THE TRACK AND FIELD (EXACT DATE NOT YET SECURED, ESTIMATED TO NOW BE IN OCTOBER).
  • REINFORCED ACCESS ROAD WAS WORKED ON (AREA ADJACENT TO LOWER FOOTBALL FIELD). 
PROJECTED WORK 7/23-18 TO 7/28/18

MS/HS

  • ROOFING  TO CONTINUE (MOVING TOWARD HIGH SCHOOL ENTRY AND OFFICES).
  • REINFORCED ACCESS ROAD WORK TO CONTINUE.
  • STEEPLE CHASE AND DRAINAGE TO BE INSTALLED AT NORTH END OF TRACK.

*NOTE: THE MAJORITY OF CONSTRUCTION ACTIVITIES IN THIS PHASE ARE EXTERIOR WORK AND ARE CONTINGENT ON WEATHER CONDITIONS.