- ICE AND WATER SHIELD AND PAPER SUBSTANTIALLY COMPLETE AT HIGH SHINGLE ROOF.
FREEVILLE
- EXISTING COMPOSITE SHINGLE ROOF REMOVED.
- ICE AND WATER SHIELD AND PAPER SUBSTANTIALLY COMPLETE.
MS/HS
- ROOFING WORK CONTINUED IN G-WING.
- AFTER SECOND RAIN IN 1 HOUR ON MONDAY NIGHT, A TEMPORARY ROOF DRAIN WAS OVERWHELMED AND THERE WAS LEAKING INTO THE BUILDING AND VARYING DEGREES OF WATER I ROOMS G-2, G-3, G-4, G-10, G-12, G-9, THE CORRIDOR AND SCIENCE STORAGE ROOM. THE MAJORITY OF THE DAMAGE WAS LIMITED TO CEILING TILES WITH A FEW BOOKS, A COUPLE SMALL APPLIANCES AND A HANDFUL OF CABINET COMPONENTS ALSO SUFFERED DAMAGE. DAMAGES ARE BEING TRACKED AND CONTRACTOR HAS RESPONDED AND IS TAKING RESPONSIBILITY.
- NEW TRACK FENCE POSTS WERE INSTALLED.
- AREAS OF EXISTING THIN ASPHALT AT TRACK WERE IDENTIFIED AND A PLAN FOR CORRECTION WAS DEVELOPED. THIS WILL HAVE AN IMPACT ON THE OVERALL COMPLETION DATE AND TURN-OVER OF THE TRACK AND FIELD (EXACT DATE NOT YET SECURED, ESTIMATED TO NOW BE IN OCTOBER).
- REINFORCED ACCESS ROAD WAS WORKED ON (AREA ADJACENT TO LOWER FOOTBALL FIELD).
PROJECTED WORK 7/23-18 TO 7/28/18
MS/HS
- ROOFING TO CONTINUE (MOVING TOWARD HIGH SCHOOL ENTRY AND OFFICES).
- REINFORCED ACCESS ROAD WORK TO CONTINUE.
- STEEPLE CHASE AND DRAINAGE TO BE INSTALLED AT NORTH END OF TRACK.
*NOTE: THE MAJORITY OF CONSTRUCTION ACTIVITIES IN THIS PHASE ARE EXTERIOR WORK AND ARE CONTINGENT ON WEATHER CONDITIONS.