7/12/19 Capital Project Update

7/12/19 Capital Project Update
Posted on 07/19/2019

We are pleased to provide the following as an update for Phase 1, 2, & 3 of the Dryden capital Improvement Project.

Work week of 7/8/19 – 7/12/19

Phase 1
o Boland's has continued to run underground electric for the score boards.
o Boland’s has completed a good deal of finish grading, spreading topsoil, rock hounding and hydro seeding.

Phase 2
Edger completed the new building foundations, waterproofing and backfill of the foundation.
o Brosh has been installing underground sanitary piping in the office end of the building.
o Boland’s removed sidewalk from the East side of the building excavated and installed new sanitary lines, man hole tie ins and backfilled all piping.

Phase 3
Siracusa has completed removal of the boilers, Cogens, water tanks, compressor and all associated pipe demo.  Duct demo was done in the locker room corridor, install of new in the locker rooms, domestic water line install continued in the locker rooms as well as the kitchen.
o Nelcorp has continued to demo existing corridor lighting and install temp lighting, pulled wire in the locker rooms and the district office and continued rough in in the kitchen and MS cafeteria.
o FAHS completed demo for the new choral room sky lights, removed corridor ceilings, removed equipment pads in the boiler room, removed exterior wall sections for the new choral room store front windows and cut in new door openings for the choral room and locker room.  Masonry was completed for the new ramps in the auditorium, misc in fills, and the locker rooms.  Tile installation continues in the locker room shower area’s and the coaches offices, prep for new corridor tile adjacent to the HS cafeteria, framing and drywall and finishing progressed in the kitchen/ MS cafeteria along with the locker rooms and Choral rooms.  New foundation footings were poured for the main entrance canopy and the new band room exterior stairs.  Asbestos abatement was completed in the band rooms and started in the HS cafeteria

Work week of 7/15/19 – 7/19/19

Phase 1 
oHale will continue with minor detail work getting ready for roofing manufacturers inspection.
o Boland’s will continue with final grading, hydro seeding and clean up

Phase 2
Edger will start install of the two bus lift tubs.
o Brosh will continue with underground sanitary piping.
o Boland’s will continue work on new storm, sanitary and water mains.

Phase 3
Siracusa will continue install of the new pool boilers, domestic water piping and insulation in the locker rooms, pour equipment pads in the boiler rooms and begin setting equipment and piping.  Duct work will continue in kitchen and locker rooms.
o Nelcorp will continue with existing light demo in the corridors and two class rooms as well as rough in in the kitchen area as well as pulling wire in various area’s.
o FAHS will start installation of the new walk in freezer/ cooler, set door frames for locker room corridor doors, continue with tile installation in both locker rooms, framing and drywall will continue for the skylight openings in the new choral space, continue to remove corridor and two class room ceilings, pour concrete for the new main entrance piers and band room stair wall, remove asbestos tile and mastic from the HS cafeteria, painting will begin for the above ceiling structure in the MS cafeteria, demolition will start in the existing band rooms and the new auditorium ramps will be poured.