6/17/19 Capital Project Update

6/17/19 Capital Project Update
Posted on 06/19/2019

The following is an update for Phase 1, 2 & 3 of the Dryden Capital Improvement Project.

Work week of 6/10/19 – 6/14/19

Phase 1
Hale has finished 90% of all roof metal and continued with detail work.
Nagel has completed the lines on the track and its ready for use.
Boland’s and Whitemore fence have continued work on the new ball fields and fencing, dug outs are being assembled.

Phase 2 
Edger has pour the first section of the new building foundation completing the South and west sides.
Boland’s has set 80% of the new underground structures and has begun install temporary fencing to secure the site.
Brosh has started the water service inside the building for domestic water and fire protection.

Phase 3
 
Framing has started in the new kitchen and middle school cafeteria along with electrical, plumbing and HVAC rough-ins.
o Masonry walls in the new boys./ girls locker rooms have progressed and are near completion and plumbing and electrical rough ins have progressed along with the wall construction.
General and theatrical demolition was completed in the auditorium.
o Framing and electrical rough in were done in the district office space.
In C13 new duct work was ran, the first of the new skylights was cut in and drywall hanging has started.

Work week of 5/17/19 – 5/21/19

Phase 1
Hale will continue to complete detail work and getting ready for manufactures inspection.
o Boland’s and whitmore will continue with field grading, dugout assembly and installing clay.

Phase 2 
Edger will continue to form and pour sections of the new building foundation walls and remaining footer section.
o The temporary site fencing will be completed.
o Boland’s will set the last of the new underground utility structures.

Phase 3 
Masonry wall in the new boys and girls locker rooms will be completed and framing of the remaining walls will continue and tile will be started on the girls side.
o In the kitchen/ MS cafeteria plumbing, electrical and HVAC rough in will continue has framing progresses.
Drywall hanging will continue in the new choral space in C13 and weather permitting the remaining two skylights will be cut in.
o Duct work will be installed in the new boys/ girls locker room.
o The install of new boilers to heat the pool will begin.