1/31/20 Capital Project Update

1/31/20 Capital Project Update
Posted on 02/11/2020

Work week of 1/27/19 – 1/31/20

Phase 2 
o Edger- has continued interior painting of interior wall, sprinkler and gas lines, installed ceiling grid in various rooms and installed hollow metal doors.
o Brosh – continued with sprinkler and air lines, installed eye wash station, and set bathroom fixtures.
o Boland’s- continued work on fuel island station, new 5000 gallon diesel tank was set.
o Knapp –Continued with interior building power system, security and lighting, wiring HVAC units.
o Siracusa – hung interior garage heating units, pipe the boilers ran heat lines and installed track bay ceiling fans.

Phase 3
FAHS – framed walls hung drywall in new nurses suite, paining and ceiling grid in the new FACS and reading rooms, installed 90% of the new auditorium seats.
o Nelcorp – wiring band area HVAC lighting, continued work on auditorium lighting and rough in of new walls in the nurses suite.
o Siracusa – plumbing in nurses suit and heat piping in the new band corridor.

Work week of 2/3/19 – 2/7/20

Phase 2
 
o Edger – will continue painting mechanical lines, doors and walls, continue installing ceiling grid and firestopping.
o Knapp - will continue with interior power, security and lighting system rough in.
o Boland’s - will continue work on the new fuel island station.
o Brosh – will continue to make final system connections, run gas lines, set interior finishes and test lines.

Phase 3 
o Siracusa – will continue with underground plumbing in the nurses suite.
o Nelcorp -  will continue work in the new nurses suite and auditorium lighting.
o Fahs –  will finish install of the new auditorium seats, flooring in the new band rooms, ceilings in the FACS room and start laminating walls in the GEN ed rooms along with finshing ceilings and hanging doors in the auditorium corridor.