1/11/21 Capital Project Update

1/11/21 Capital Project Update
Posted on 01/11/2021
Work the Week of 12/28/2020 - 1/01/2020

Phase 2
Edger –CO Work Substantially complete.
Boland’s – Substantially Complete.
Brosh– Substantially Complete.
Knapp – Substantially Complete.
Siracusa - Substantially Complete.
Day - Worked on change orders and punch lists.

Phase 3
FAHS –  Vestibule doors, DES tall cabinet relocation and misc. paint touch up. MS/HS CO and Punchlist work.  
Nelcorp - 
Siracusa - 
Syracuse Scenery - 
Boland’s –
Day-  Worked on programming

Phase 4
FAHS –  Worked on Punch lists.  
Schuler Hass –  
Petcosky- Substantially Complete

TURF Interior
Petcosky  – Darkroom eyewashes and sink plumbing connections continued.
Edger - Waiting for remaining casework and counters.
John  Mills Electric- Receptacles & switches were installed

Work the Week of 1/04/2020 - 1/08/2020

Phase 2
Edger –Substantially complete.
Boland’s – Substantially Complete.
Brosh– Substantially Complete.
Knapp – Substantially Complete.
Siracusa - Substantially Complete.
Day - Worked on change orders and punch lists.

Phase 3
FAHS –  Vestibule doors and paint/finishes. MS/HS CO and Punchlist work. Routered in for stage floor light.
Nelcorp - Misc Punch List, fiber optic line to Maintanance building, intrusion wiring.
Siracusa - Misc. Punch lists, condensate at DES kitchen, cabinet heater reinstalled in vestuable, additional valves installed.
Syracuse Scenery - 
Boland’s –
Day-  Working on programing and punch lists.

Phase 4
FAHS –  Substantially Complete.  
Schuler Hass –  
Petcosky- Substantially Complete

TURF Interior
Petcosky  – Art Room Sink rough-in
Edger - Waiting for remaining casework and counters.
John  Mills Electric- Data installed.

Work the Week of 1/11/2020 - 1/15/2020

Phase 2
Edger –Substantially complete.
Boland’s – Substantially Complete.
Brosh– Substantially Complete.
Knapp – Substantially Complete.
Siracusa - Substantially Complete.
Day - Working on change orders and punch lists.

Phase 3
FAHS –  Vestibule paint/finishes. 
Nelcorp - Misc. Punch List, stage floor light installation/connections intrusion wiring.
Siracusa - Misc. Punch lists.
Syracuse Scenery - Waiting until in-person meetings are again permissible to schedule final audio training.
Boland’s –
Day-  Working on programing and punch lists.

Phase 4
FAHS –  Substantially Complete.
Schuler Hass – Working on Punchlist - Wednesday.
Petcosky- Substaintially Complete

TURF Interior
Petcosky  – HVAC roof equipment being set mid-week.
Edger - Waiting for remaining casework and counters (scheduled to ship by the end of the week.). Set roof curbs for darkroom HVAC equipment. Auditorium wing stairs terrazzo materials scheduled to ship by the end of the week.
John  Mills Electric- Fire Alarm Devices and power to HVAC equipment.
Day - Providing damper for exhaust fan to Petcosky.