11/9/18 Capital Project Update

11/9/18 Capital Project Update
Posted on 11/09/2018

The following is an Update for Phase 1 of The Dryden CSD 2017 Capital Improvement Project.

Work the Week of 11/05/18 - 11/09/18

MS/HS

  • Track Fencing Fabric - Nearly complete
  • Steel for main field Scoreboard delivered and welded

Projected Work Week of 11/12/18 - 11/16/18

DES

  • Ladder Install and RTU adjusted (crane on Monday).

MS/HS

  • Roofing over MS Gym (Crane Monday and 2 days after school

  • (Wed & Thurs)

  • Roof detail and metal work.
    Main Field Score Board deliver and install.