The following is an Update for Phase 1 of The Dryden CSD 2017 Capital Improvement Project.
Work the Week of 11/05/18 - 11/09/18
MS/HS
- Track Fencing Fabric - Nearly complete
- Steel for main field Scoreboard delivered and welded
Projected Work Week of 11/12/18 - 11/16/18
DES
- Ladder Install and RTU adjusted (crane on Monday).
MS/HS
- Roofing over MS Gym (Crane Monday and 2 days after school
- (Wed & Thurs)
- Roof detail and metal work.
Main Field Score Board deliver and install.