11/29/19 Capital Project Update

11/29/19 Capital Project Update
Posted on 12/04/2019

Work week of 11/25/19 – 11/29/19

Phase 2 
o Edger- Started installation of the insulated metal roof panels, continued m3etal stud framing and installed misc blocking.
o Brosh - worked on sprinkler and air line rough in.
o Boland’s- worked on underground storm pipe.
o Knapp – power and lighting rough in office and truck bay area.

Phase 3
o FAHS –installed ceiling sound panels in C113, complete grinding and grout for the senior seating terrazzo, installed wall tile in the band corridor, completed masonry at the band area mezzanine, completed grid for the kitchen/ dish room ceilings, installed the kitchen kettle drain pan, completed stair framing in the auditorium, and worked on drywall and finishing in the band rooms and kitchen, the mechanical platform in the food service room was installed.
o Nelcorp – light upgrades G-wing class rooms, lighting rough in kitchen.
o Siracusa – sanitary tie in under kitchen, heat pipe in new FACS sewing room.

Work week of 12/2/19 – 12/6/19

Phase 2 
o Edger will complete install of he insulated metal roof panels. 
o Knapp will continue interior wall rough-in the offices.
o Boland’s will continue with install of remaining underground structures and start the fuel island foundations.
o Brosh will continue with  above grade sanitary, venting, domestic water and sprinkler piping.

Phase 3
o Siracusa – will continue with heat pipe runs, insulation and fin tube assembly in the HS cafeteria.
o Nelcorp -  will continue branch conduit rough in in the auditorium, rough in of the band spaces and continue class room light upgrades in G wing and install lights along with the wood ceiling install.
o Fahs – will complete terrazzo flooring in the HS café senior seating area, start installing the wood ceiling in the kitchen serving area’s, continue with drywall finishing in the new band rooms, continue with tile installation in the band corridor and start tile in the new band area bathrooms, kitchen equipment and delivery will start, framing of new walls will start in the new FACS sewing room and start paint in the band rooms.