11/12/20 Capital Project Update
Posted on 11/12/2020
Work week of 11/09/2020 – 11/13/2020
Phase 2
Edger – Substantially Complete - Working on remaining Punch List Items
Boland’s – Substantially Complete .
Brosh– Substantially Complete .
Knapp – Substantially Complete.
Siracusa - Working on Punch lists and Change Orders.
Day - working on change orders and punch lists.
Phase 3
FAHS – Installation of remaining countertops clean up and punch list items worked on around the MS/HS.
Nelcorp – Misc. Punch List Items.
Siracusa – Worked on some valve replacements, installed sinks and dishwasher in FACS and Punch List Items.
Syracuse Scenery -
Boland’s – Paving at former maintenance building site.
Phase 4
FAHS – Working on Punch lists.
Schuler Hass –
Petcosky- Factory technician replaced part on Cassavant UV.
TURF Interior
Petcosky –
Edger - Applied Block filler and start painting of darkroom. Temporary wall was removed and doors were installed. Tile work in corridors continues.
John Mills Electric-
Work week of 11/16/2020 – 11/20/2020
Phase 2
Edger – Substantially Complete - Working on remaining Punch List Items
Boland’s – Substantially Complete .
Brosh– Substantially Complete .
Knapp – Substantially Complete.
Siracusa - Working on Punch lists and Change Orders.
Day - working on change orders and punch lists.
Phase 3
FAHS – Installation of remaining countertops clean up and punch list items will be worked on around the MS/HS. Working on doors and finishes in “E” Wing vestibule.
Nelcorp – Misc. Punch List Items.
Siracusa – Working on some valve replacements, installed sinks and Punch List Items.
Syracuse Scenery -
Boland’s – Painting New DES Parking Lot lines if weather allows.
Phase 4
FAHS – Working on Punch lists.
Schuler Hass – Working on Punch Lists
Petcosky- Cassavant Nurses sink to be installed.
TURF Interior
Petcosky –
Edger - Continue painting of darkroom. Tile work in corridors is scheduled to be close to complete.
John Mills Electric-