11/12/20 Capital Project Update

11/12/20 Capital Project Update
Posted on 11/12/2020
Work week of 11/09/2020 – 11/13/2020

Phase 2
Edger – Substantially Complete - Working on remaining Punch List Items
Boland’s – Substantially Complete .
Brosh– Substantially Complete .
Knapp – Substantially Complete.
Siracusa - Working on  Punch lists and Change Orders.
Day - working on change orders and punch lists.

Phase 3
FAHS – Installation of remaining countertops  clean up and punch list items worked on around the MS/HS. 
Nelcorp – Misc. Punch List Items.
Siracusa – Worked on some valve replacements, installed sinks and dishwasher in FACS and Punch List Items.
Syracuse Scenery - 
Boland’s – Paving  at former maintenance building site.

Phase 4
FAHS –  Working on Punch lists.
Schuler Hass – 
Petcosky- Factory technician replaced part on Cassavant UV.
TURF Interior 
Petcosky  – 
Edger - Applied Block filler and start painting of darkroom.  Temporary wall was removed and doors were installed.  Tile work in corridors continues.
John Mills Electric-
 
Work week of 11/16/2020 – 11/20/2020

Phase 2
Edger – Substantially Complete - Working on remaining Punch List Items
Boland’s – Substantially Complete .
Brosh– Substantially Complete .
Knapp – Substantially Complete.
Siracusa - Working on  Punch lists and Change Orders.
Day - working on change orders and punch lists.

Phase 3
FAHS – Installation of remaining countertops  clean up and punch list items will be worked on around the MS/HS.   Working on doors and finishes in “E” Wing vestibule.
Nelcorp – Misc. Punch List Items.
Siracusa – Working on some valve replacements, installed sinks  and Punch List Items.
Syracuse Scenery - 
Boland’s – Painting New DES Parking Lot lines if weather allows.

Phase 4
FAHS –  Working on Punch lists.
Schuler Hass –  Working on Punch Lists
Petcosky- Cassavant Nurses sink to be installed.
TURF Interior 
Petcosky  – 
Edger - Continue painting of darkroom.  Tile work in corridors is scheduled to be close to complete.
John Mills Electric-