10/1/18 Capital Project Update

Posted on 10/01/2018
Work the Week of 9/24/18-9/28/18

DES
o Roof Detail and Metal Work
MS/HS
o Some misc. Roofing Detail and Metal Work
*Track fence "fabric"
o Asphalt Paving of Track

Projected Work Week of 10/1/18-10/5/18

DES
o Roof Detail and Metal Work
MS/HS 
o  Some misc. Roofing Detail and Metal Work
*Roofing over Library
o Additional Construction Fencing installed for Diamond Field Work
o Grading Work at Upper fields
o Backstop Removal

*Note: The majority of construction activities in this phase are exterior work and are contingent on weather conditions. The forecast for the week of 10/1-10/5 unfortunately does not look favorable.