7/7/20 Capital Project Update

7/7/20 Capital Project Update
Posted on 07/07/2020
Work week of 6/29/20– 7/3/20

Phase 2 
Boland’s – has been working on touch up final grades and hydro seeding along with installing the second fire hydrant the town  requested
Knapp –  Has been making final terminations to equipment and panels.

Phase 3
FAHS – Roof trusses have been set on the new events center and the plywood roof sheathing installed, terrazzo floor in fills were done at the MS main entrance and several other rooms, drywall hanging and finishing continue in the new FACS room, class room ceilings continued to be replaced, the last of the removes have been removed and re-install is nearly complete for all rooms. The tile floor was set in the new nurses suite and abatement of the old nurses suite was completed
Nelcorp – CMU rough in of the events facility, continued with lighting upgrades at HS/MS and DES
Boland’s – Has continued to form and pour new curbs and side walks and grade and top soil
Siracusa – complete duct rough in of the concession building.

Phase 4
FAHS – (CASS) has been finishing drywall and painting ,(Freeville) Drywall finishing and painting
Schuler – Haas – has been working on light change outs, and fire alarm and power rough in at both schools
Potoski and Son – has been roughing in plumbing and HVAC and began install new equipment.

TURF – Clark has been excavating and installing the field underground water retention system, pour concrete around the perimeter of the field along with the Concrete pad at the North end.
 
Work week of 6/15/20 – 6/19/20

Phase 2 
Knapp – will continue with installing electrical fixtures and devices along with labeling
Boland’s – will continue to dress up final grades areas and hydroseeding.

Phase 3
Siracusa – will continue re- route the freezer cooler drain, demo the roof leader in E wing
Nelcorp -   will start install of the senior seating lighting and continue changing out of class room lights
Fahs – Will continue demolition of the old “E” wing section of the building, continue with the new shared entrance frames and glass, continue painting the pool ceiling with final coat to be complete this week, blocking will be installed for the new lockers, case work will continue to be installed in the new FACS and reading rooms, the roof and metal siding will be complete on the concessions building and the ceiling drywall wall will all be hung and the finishing starting, foundations will be started for the new entrance canopy at DES
Boland’s – will continue to form and pour curbs and walks.
 
Phase 4
FAHS – will be continuing drywall finishing and painting at both schools.
Schuler – Haas  - will continue with light change out and power and fore alarm rough in both buildings
Potoski and Son – will continue duct and plumbing rough ins above ceilings.
 
TURF
Clark – will continue work on the drainage system for the new field.

Pool ceiling

E wing demo

Lighting layout

DES loop