4/3/20 Capital Project Update

4/3/20 Capital Project Update
Posted on 04/03/2020
MS/HS

o The Nurses Suite - Currently receiving finishes -Accessories and casework in July 
o FACS Sewing- Finishes nearly completed - Casework in July 
o General Classrooms- Currently receiving finishes - casework in July 
o Robotics - Demolition to begin 4/6 including abatement - renovations  to follow - scheduled to complete this Summer
o Wrestling Room & Athletic Storage - Demolition to begin 4/6 including abatement - renovations  to follow - scheduled to complete this Summer
o MS Classrooms Ceilings (1st Floor) - Ceilings demolition and replacement and new lighting to continue- Scheduled to complete prior to 4/15 class restart.
o Corridors- Terazzo starting and ceiling and light replacement on going.
o Auditorium- Glass railings to install next  week.

Concession Building 
o Excavation and foundations to begin 4/6 and buildout to follow.

DES

o Lighting Replacement beginning and ongoing.
o Parking and site work is currently scheduled to begin at the End of June.

Transportation Center
o Bus lifts and Bus Wash installation starting next week.
Sidewalks being installed.
o Water service is connected.
o Gas service is connected NYSEG to turn in within the next week.
o Paving to begin after concrete work (mid/late April).
o Mechanical Systems are nearly complete.
Punchlists are beginning.

Cassavant & Freeville
o Submittals are ongoing
o Construction scheduled to begin at the End of June.

Turf Project

o Waiting to be assigned to a 3rd Party Reviewer.
o Plans at vendors for quotes under Cooperative Bidding.