2/18/20 Capital Project Update

2/18/20 Capital Project Update
Posted on 02/18/2020

Work week of 2/10/19 – 2/14/20

Phase 2 
o Edger- Has continued with interior finish painting of structural steel, walls and doors, ceiling tile and grid is being installed in the offices.
o Brosh – 90% with all gas, air and plumbing systems and final connections.
o Knapp –Continued with interior building power system, fixtures have been delivered, the generator and transfer switch have been installed.
o Siracusa – has been installing line sets, insulating pipe and making final duct connections.

Phase 3
o FAHS – Completed flooring in the band area, installed ceilings and tile in the FACS and reading rooms, installed the auditorium sound booth, started wall laminating the GEN ED rooms, installed the new exterior doors to the FACS and band rooms, and installed doors and hardware in the band rooms.
o Nelcorp – continued on finishes in the band area and worked on stage power and lighting.
o Siracusa – completed underground sanitary and domestic water rough ins for the new nurses suite and fitness center bathrooms.

Work week of 1/17/19 – 1/21/20

Phase 2
 
o Edger – will be working on finishing ceilings and paint, prepping for flooring installation and millwork.
o Knapp – will be working on electrical finishes, equipment connections and completing wiring of the generator and transfer switch.
o Brosh – will be setting and hooking up the new air compressor and making final sprinkler connections.
o Siracusa – will be making final connection for office area diffuser’s insulation heat pipe and installing mezzanine duct work.
o NYSEG – crews have staged along Mott road for the gas line extension to the new building.

Phase 3
 
o Siracusa – will work on auditorium heat runs, set GEN ed room UV’s and complete nurses suite vent piping.
o Nelcorp -  will continue with band area finishes and stage lighting and power.
o Fahs – Will continue with renovations on the Gen ed rooms, demo the corridor ceiling East of the big Gym and re-install, finish installing band/Aud doors and hardware, finish paint and flooring, and start carpet in the auditorium.

garage