1/24/20 Capital Project Update

Work week of 1/20/19 – 1/24/20

Phase 2 
o Edger- has completed drywall finishing, has started painting structural steel, first coat of paint on the bus wash block walls, started office area ceiling grid, applied spray on fire proofing to the structure in the fluid storage room and started hanging wood doors.
o Brosh – has resumed work on fire protection lines, continued installation of air lines and accessories, fixtures for the bathroom have been delivered.
o Boland’s- continued work on the new fuel island structure, trenched and backfilled for underground gas lines, poured the generator concrete pad and prepped for the hot box pad.
o Knapp –Continued with interior building power system, rough I forth generator an switch gear.
o Siracusa – has set the new boilers, started to install ceiling hung heating units, started the install of the truck bay ceiling fans and continued with duct work install.

Phase 3
o FAHS – Completed demolition of the existing HS kitchen and started to frame new walls for what will be the new nurses suite, auditorium seating has been delivered and install is underway, remaining ceiling panels have been hung in the new band room, toilet partitions were installed in the band bathrooms, auditorium corridor drywall soffits were framed and drywall is being hung and finished.  Drywall finishing in the FACS sewing room was completed, stage refinishing and painting was completed and the installation of the auditorium wood ceiling continued to progress.
Nelcorp – changed out the MS cafeteria electrical panel, pulled wire for HVAC units on the band mezzanine, continued with lighting upgrades in the HS wing and started rough in work in the new nurses suite.
o Siracusa – changed the school backflow preventer, and worked on duct terminations in the band area.

Work week of 1/27/19 – 1/31/20

Phase 2
 
o Edger – will continue painting interior walls and structural steel, continue with wood door installation and office area ceiling installation.
o Knapp - will pull 3 phase wire in from the road, set and start to wire the automatic transfer switch and start light fixture installation.
o Boland’s - will continue work on the new fuel island.
o Brosh – will set bathroom plumbing fixtures and continue with sprinkler line installation.

Phase 3 
o Siracusa – will start underground plumbing in the new nurses suite and continue with duct termination in the band area.
o Nelcorp -  will install the HS gyms new wrestling light, complete the entrance canopy lighting and start the senior seating permanent lighting.
o Fahs –  Will continue with installation of the new auditorium seating, continue framing in the new nurses suite, demo the portions of the existing slab I the nurses suite for under ground plumbing, install windows and exterior door in the new FACS sewing room, start paint in the FACS room and start the install of flooring in the band area rooms.

Washbay

nurses framing

band clouds

generator

aud seating