1/13/20 Capital Project Update

1/13/20 Capital Project Update
Posted on 01/12/2020

Work week of 1/30/19 – 1/10/20

Phase 2 
o Edger- Office drywall hanging and finishing is complete and first finish coat of paint is on, ceramic tile installation in the bathroom is complete, installation of aluminum doors is progressing, exterior building trim is nearly complete and gutters have been installed along with roof snow guards, painting has started in the first floor mechanical rooms.
o Brosh – No work.
o Boland’s- progressing with the fuel island, foundations have been backfilled and Bollards have been set.
o Knapp –Continued with interior building power system, security and lighting rough in, wires are being pulled to sub panels.

Phase 3
o FAHS – Demolition of the existing HS kitchen has started, Band area ceramic tile was completed, Band area corridor acoustic tile and wood ceiling installation has started, finishing touches were put on the new stage stairs, ceiling panels are being fabricated for the floating ceiling in the band room, masonry work on the new window openings for the new FACS room is nearly complete. 
o Nelcorp – light upgrades G-wing class rooms and corridors continued, installation of light fixtures in the band area started as well as devices, magnetic hold opens were added to all kitchen doors.
o Siracusa – Demo of old HS kitchen plumbing and gas systems has started as well as rough in for the new FACS sewing room.

Work week of 1/13/19 – 1/17/20

Phase 2
 
o Edger – will start acoustic ceilings In the office area, remaining office area ceramic tile will be completed, painting of the common spaces in the building.
o Knapp will continue with interior power, security and lighting system rough in.
o Boland’s will continue work on the new fuel island and pour pads for the Hot box and  generator and trench for the gas line sleeve.

Phase 3 
o Siracusa – will set fixtures in the new band area. bathrooms, move heat lines at the auditorium and complete demo in the existing high school cafeteria.
o Nelcorp -  will continue HS lighting upgrades and continue with finishes in the new band area and auditorium.
o Fahs –  Will continue with corridor and room ceilings in the band area, finish demolition and start framing in the old HS cafeteria/ new nurses suit, and continue drywall finishing  in the new FACS room as well as complete demolition of the first 2 Gen ed rooms. Stage refinishing will also begin.

Band Corridor

Bustile

kids

kitchen