The following is an update for Phase 1, 2, & 3 of the Dryden Capital Improvement Project.
Work week of 4/1519 – 4/19/19
Phase 1
o Work resumed on roofing metal install, no work on fields, to wet after an inch of rain
Phase 2
o Minimal work was done on the transportation site this week due to saturated soils from rain
Phase 3
o Asbestos tile and mastic removed from kitchen offices
o Asbestos abatement for ACM discovered in boys locker room offices
o New footer and concrete wall poured in #C13
o All kitchen equipment removed
o All heaters from kitchen area and locker rooms removed
o Demolition of boys locker room began, all lockers, bases, ceilings, and several block walls already removed. Additional ACM pipe fittings found on hot/ cold water piping
o Roof penetration done for dryer
o Concrete pad poured for new cooler
o Temp wall built closing west entrance by kitchen
Work week of 4/15/19 – 4/19/19
Phase 1
o Nagel scheduled to start work on the track on 4/22
o Hale roofing will continue with the install of roofing metal
Phase 2
o Boland’s will be continue getting the site to sub grade, removing excess material
Phase 3
o Asbestos Abatement for locker room pipe fittings
o Demolition of kitchen walls ceilings and flooring
o Continue demolition of existing boys locker room
o Complete hook up of relocated washer and dryer in the weight room