4/5/19 Capital Project Upate

Work week of 4/1/19 – 4/5/19 

Phase 1

o   No work

Phase 2 

o   Completed all stump grinding and Tree clearing  contractor demobilized all equipment.  Boland’s delivered their Dozer and began rough grading and installed the stabilized construction entrance.

Phase 3

o   Asbestos abatement contractor mobilized and abated floor mastic in room #C13, scheduled to be 100% removed on 4/5.

o   Fahs installed temporary wall in the high school cafeteria.

o   Demolition of existing slab room #A11 for new bathroom.

o   Nelcorp has been running feeder conduit to new panels that will be located in the auditorium during summer renovations.

 
Work week of 4/8/19 – 4/12/19

Phase 1 

o   Boland’s will mobilize Monday to resume work on the athletic field at the HS/MS.

Phase 2

o   Boland’s will be grading new transportation site to sub grades.

Phase 3

o   Asbestos Abatement will demobilize and tear down all containment.

o   Demolition will resume in room #C13 where FAHS will be saw cutting and removing a section of the sloped concrete slab and grading and starting to form footing for the new wall.

o   Temporary freezer and refrigerated units will be delivered and hooked up.

o   Nelcorp will continue on new panel feeders for the auditorium panels.

o   District personnel will be will be moving out of kitchen offices and storage and emptying the Girls locker room #A31 both scheduled to have demolition start on 4/15.