Work week of 4/1/19 – 4/5/19
Phase 1
o No work
Phase 2
o Completed all stump grinding and Tree clearing contractor demobilized all equipment. Boland’s delivered their Dozer and began rough grading and installed the stabilized construction entrance.
Phase 3
o Asbestos abatement contractor mobilized and abated floor mastic in room #C13, scheduled to be 100% removed on 4/5.
o Fahs installed temporary wall in the high school cafeteria.
o Demolition of existing slab room #A11 for new bathroom.
o Nelcorp has been running feeder conduit to new panels that will be located in the auditorium during summer renovations.
Work week of 4/8/19 – 4/12/19
Phase 1
o Boland’s will mobilize Monday to resume work on the athletic field at the HS/MS.
Phase 2
o Boland’s will be grading new transportation site to sub grades.
Phase 3
o Asbestos Abatement will demobilize and tear down all containment.
o Demolition will resume in room #C13 where FAHS will be saw cutting and removing a section of the sloped concrete slab and grading and starting to form footing for the new wall.
o Temporary freezer and refrigerated units will be delivered and hooked up.
o Nelcorp will continue on new panel feeders for the auditorium panels.
o District personnel will be will be moving out of kitchen offices and storage and emptying the Girls locker room #A31 both scheduled to have demolition start on 4/15.