9/14/18 Capital Project Update

9/14/18 Capital Project Update
Posted on 09/14/2018
The following is an Update for Phase 1 of The Dryden CSD 2017 Capital Improvement Project

Work the Week of 9/10/18-9/14/18

DES
o Roof Detail and Metal Work
MS/High School
o Roofing work over Offices, Technology and Corridors.
o Roofing Detail and Metal Work over High School Offices and District Offices
o Environmental Protection installed for Diamond Field Work
o Drainage Work at upper fields
o Installation of Jump Pit Sand

Projected Work Week of 9/17/18-9/21/18

DES
o Roof Detail and Metal Work
MS/High School
o Roofing work continues over Technology and Corridors.
o Roofing Detail and Metal Work over District Offices and Canopies
o Roofing may start over Library
o Construction Fencing installed for Diamond Field Work
o Drainage Work at upper fields
o Grading Work at Upper fields
o Backstop Removal
o Asphalt Paving of Track
o Removal and Installation of Main Field Scoreboard

*Note: The majority of construction activities in this phase are exterior work and are contingent on weather conditions.