6/7/19 Capital Project Update

6/7/19 Capital Project Update
Posted on 06/11/2019

The following is an update for Phase 1, 2 & 3 of the Dryden Capital Improvement Project.

Work week of 6/3 - 6/7

Phase 1  
Hale has continued to complete sections of roof edge metal, scupper and flashing.  Boland’s and their sub Whitmore fence have continued work on the new athletic fields and fencing
 Foundations for the new score boards were poured.

Phase 2 
o Boland has begun underground utility install work and Edger has excavated and poured the first sections of the new buildings foundation footings.

Phase 3
 
Work is moving along in several area’s, new block walls are being laid by the mason contractor in the new boys and girls locker along with electrical and plumbing rough in.  Door frames area  being set in A38 and drywall is started.  Drywall was delivered for the new choral space along structural steel has been installed to reinforce the new skylight openings, electrical inspection has been completed along with new above ceiling branch conduit being run.  New HVAC roof top units

Work week of 6/10 - 6/14

Phase 1

Phase 2
 
Edger will continue with install of the concrete foundations for the new building and Boland’s will continue installing underground utilities.

Phase 3
 
Work in the boys/ girls locker room will continue as we see block walls continued to be laid up, electrical, plumbing and HVAC rough in’s will progress along with he walls.  Drywall will be being hung in room #A38 along with new heating control wiring.  Drywall will begin in the new choral space along with HVAC rough in.  Kitchen demo will continue with the new window openings being finished and the new concrete topping slab being poured