4/13/20 Capital Project Update

4/13/20 Capital Project Update
Posted on 04/13/2020

Work week of 4/6/20– 4/10/20

Phase 2 

    • Phase 3
      • FAHS – Demo corridor area’s of Fritz tile, prep and pour terrazzo both corridors, demo lockers and in fill opening, demo’d more class rooms ceilings and installed new grid in tile in 5 class rooms, broke ground on the new events facilities building completing the underground changes to the existing sanitary system.  Completed demo in the existing weight room, moved weight equipment, painted the nurses suite and finished the Gen ed room floors
      • Nelcorp – lighting upgrades at both the High school and started on the lighting upgrades to DES
      • Siracusa – changed out the existing heat exchanger in the boiler room and worked on punch list items

    Work week of 4/13/20 – 4/17/20

    • Phase 2 –
      • Edger – will complete  the installation of the two new bus lifts
      • Knapp – will continue with installing electrical fixtures and devices and power up HVAC units and complete bus wash power changes
      • Siracusa – will continue  to fill the heating system and start HVAC units
      • Boland’s – will continue forming and pouring curbs and sidewalks and grading the site and continue pavement sub base install
    • Phase 3 –
      • Siracusa – will demo duct work in various corridors
      • Nelcorp -   will continue class room ceiling lighting upgrades in the High school wing and DES, Install lights in class rooms as ceilings are installed
      • Fahs – Will continue with demo and put back of class room ceilings, start the grinding of new corridor terrazzo, start framing in the old weight room, abate asbestos panels in the new robotics room, finish drywall locker in fills, paint existing stage walls and ceilings, dig form and pour footing for the new events facility and start forming the foundation walls, floors in the nurses suite will be self leveled and flooring install will start, painting will also continue on nurses suite door frames. 