The following is an update for Phase 1, 2, & 3 of the Dryden Capital Improvement Project.
Work week of 3/11/19 – 3/15/19
Phase 1
o Whitmore fence installing foundation and poles for new backstops
Phase 2
o Brush and tree clearing is nearing completion well ahead of the April first dead line.
Phase 3
o Demolition of Seating, walls, stage ceiling, radiant heating and electrical systems are well under way in C13
o Removal of existing electrical fixtures and wiring has been removed from Room A11
o Samples were taken of suspected ACM in room #C13, results will be available on 3/18
Work week of 3/18/19 – 3/22/19
Phase 1
o Whitmore fence will continue work on the new backstops at the high school
Phase 2
o Remaining brush will be cleared and Boland’s will grind stumps and clean up site at the new transportation building site
Phase 3
o General demolition of Room #C13 will continue with the remaining wall and stage demolition being completed
o Room #A11 floors will be saw cut and removed for new cooler and under ground plumbing along with existing case work and drywall patricians
o The entrance canopy at the exterior door adjacent to C13 will be removed on 3/18
o All trees slated for removal at DES will be removed and disposed of on 3/18