3/15/19 Capital Project Update

3/15/19 Capital Project Update
Posted on 03/15/2019

The following is an update for Phase 1, 2, & 3 of the Dryden Capital Improvement Project.

Work week of 3/11/19 – 3/15/19

Phase 1  

o   Whitmore fence installing foundation and poles for new backstops

Phase 2

o   Brush and tree clearing is nearing completion well ahead of the April first dead line.

Phase 3

o   Demolition of Seating, walls, stage ceiling, radiant heating and electrical systems are well under way in C13

o   Removal of existing electrical fixtures and wiring has been removed from Room A11

o   Samples were taken of suspected ACM in room #C13, results will be available on 3/18


Work week of 3/18/19 – 3/22/19

Phase 1

o   Whitmore fence will continue work on the new backstops at the high school

Phase 2

o   Remaining brush will be cleared and Boland’s will grind stumps and clean up site at the new transportation building site

Phase 3

o   General demolition of Room #C13 will continue with the remaining wall and stage demolition being completed

o   Room #A11 floors will be saw cut and removed for new cooler and under ground plumbing along with existing case work and drywall patricians

o   The entrance canopy at the exterior door adjacent to C13 will be removed on 3/18

o   All  trees slated for removal at DES will be removed and disposed of on 3/18