11/1/19 Capital Project Update

11/1/19 Capital Project Update
Posted on 11/01/2019

Work week of 10/28/19 – 11/1/19

Phase 2 
o Edger- continued with installing liner panels and metal stud framing for the new offices
o Brosh - worked on sprinkler and air line rough in
o Boland’s- continue with the installation of the new water main from the high school, finished grading and rolling the connecting road preparing for pavement
o Siracusa has been rough in duct work and heat piping

Phase 3
FAHS – started demolition of the existing pool lockers, poured terrazzo for the HS cafeteria floor, installed floor tile in base in the new joint kitchen, installed metal studs and drywall in the new band area, installed structural steel and decking for the band area mechanical mezzanine, started installing new display  cases by the high school gym, caulk pre cast at the new cafeteria windows, installed window blinds in C113 and cafeteria, formed the ramps and the sound booth area in the auditorium
o Nelcorp – has been roughing in branch circuits on  the stage in the auditorium, installing skylight lights in C114, finished power to backboards in the HS gym and set the hand hole for canopy lights
o Siracusa – rough in carrier, waste and domestic water for the new band area bath rooms, duct rough in in the band rooms and complete the pool piping

Work week of 11/4/19 – 10/8/19

Phase 2
o Edger will start install of the exterior building insulated panels
o Knapp will start interior wall rough-in the offices
o Boland’s will continue work running the water main and pave the road from he HS parking lot to the edge of the woods
o Brosh will continue with  above grade sanitary, venting, domestic water and sprinkler piping

Phase 3
oSiracusa – will continue rough in of both HVAC and plumbing in the band rooms
o Nelcorp -  will continue branch conduit rough in in the auditorium, rough in of the band spaces and misc demo
o Fahs – will complete pouring of the HS cafeteria terrazzo and start the grinding process, tile work will continue in both the joint kitchen and the senior seating area demo of the existing pool room lockers will be completed, the mezzanine deck for the band area bathrooms will be poured, trophy cases by the HS gym will be installed, drywall and framing will continue in the band rooms and misc punch list work will be addressed in various areas.