10/11/19 Capital Project Update

10/11/19 Capital Project Update
Posted on 10/16/2019

Work week of 10/7/19 – 10/11/19

Phase 2 
o Edger continued with installing liner panels, poured both mezzanine concrete decks, started the exterior split faced block, filled bollards and began prep for the exterior building apron pours.
o Brosh worked on sanitary and domestic and sprinkler rough in.
o Boland’s has been running the new water main between the High school and the transportation building.

Phase 3
o Siracusa has ben working on pool equipment piping, heat piping in the kitchen rough in for the new band area bathrooms.
o Nelcorp has been changing out the lights in the high school gym, piping and wiring of pool equipment and rough in in the new band rooms.
o FAHS – the high school cafeteria ceiling was completed, tile progressed on the Cafeteria walls, drywall and finishing continued in the kitchen, corrective work was started on the new lockers, masonry walls along with metal stud framing progressed in the new band room area, glass panels were installed and tile completed in the pool. 

Work week of 10/7/19 – 10/11/19

Phase 2 
o Edger will continue with exterior split faced block and interior liner panels and start interior metal stud framing and pour building aprons.
o Knapp will continue rough-in walls.
o Boland’s will continue work running the water main.
o Brosh will continue with  above grade sanitary, venting, domestic water and sprinkler piping.

Phase 3
 
o Siracusa – will continue with work on the pool equipment, heat rough in in the cafeteria/ kitchen and rough in of the new band area bathrooms

Campus hosted an appreciation lunch for all Phase III workers to show thank for all their continued hard work!